Horace Mann Renovation Update
At Horace Mann, structural work continues including the installation of columns, beams, and steel channels and frames. Selective brick and roof parapet demolition continues as does lintel abatement as needed. Layout for interior spaces is ongoing. Learn more about the Horace Mann Renovation.
Meier Hall Addition
At the Meier Hall addition, foundation work continues. Concrete pouring operations for the slab-on-deck are commencing.
The construction manager will make the physical connections to the Meier Building this summer. In addition, they will also work on installing a fire curtain at specific corridor and stairwell areas. Mobilization for this work is commencing including mechanical make safe work, abatement, demolition of windows and walls (to make way for the new bridge connections), and installation of temporary partitions. Learn more about the Meier Hall Addition.
Decarbonization Project Update
Drilling, looping, and grouting for the project's geothermal wells continues. Interior demolition within the Central Utility Plant continues.